The dismantling of the cooling tower of the Mülheim-Kärlich nuclear power plant was successfully completed.

It is done! The 162 m high cooling tower of the decommissioned Mülheim-Kärlich nuclear power plant is history. On Friday, 8/9/2019, shortly after 3:30 p.m., we carried out the controlled and safe collapse of the cooling tower thanks to the use of a novel demolition technology. In the video you can see the spectacular completion of the work on the dismantling of the cooling tower of the Mülheim-Kärlich nuclear power plant.

The Rhein-Zeitung also reported on the event, which was attended by numerous onlookers. You can find the article here (in German)

“It’s gone: The cooling tower is now rubble and dust”

Rhein-Zeitung, Edition B, dated 8/10/2019, page 17


Article by Damian Morcinek

With kind permission of the Rhein-Zeitung newspaper

We would like to take this opportunity to thank all those involved in the project and our suppliers for their constructive cooperation. Thanks to them the environment that enabled this outstanding performance was created.

Our thanks also go to our employees, whose commitment was a decisive contribution to the success of the project.

Successful dismantling of the cooling tower of the Mülheim-Kärlich nuclear power plant
Successful dismantling of the cooling tower of the Mülheim-Kärlich nuclear power plant
Successful dismantling of the cooling tower of the Mülheim-Kärlich nuclear power plant
The MB Spezialabbruch team