Together with the TU Dresden and IBL-hydronic, we are working on the MAMA process (machine-based, automated, unmanned, demolition process) for the RDB 100i.
Continue readingSequential Collapse
We have successfully applied the method of a safely induced controlled sequential collapse for the demolition of the cooling tower of the nuclear power plant in Mülheim-Kärlich.
Continue readingRDB 100
The RDB 100 enables unmanned, remote-controlled demolition of tall structures with a linear structure and offers increased safety for personnel.
Continue readingDrop Anchor
The heavy-duty fastening device (drop anchor) is used to fasten loads to building structures where the wall panel has to be anchored.
Continue readingHydroshield
The Hydroshield is a barrier created with water in a container, which is used to clean air contaminated with suspended particles.
Continue readingCrane Track
In spring 2017, the dismantling work began on Units 7 and 8 of Plant IV of the Lubmin / Greifswald NPP using a specially designed crane track.
Continue readingWire Saw
A wire saw is often used to process components with large cutting depths and to cut tubular structures to size.
Continue readingWall Saw
Saw blades with a diameter of up to 1,600 millimeters are used for the wall saw, which allows for cutting depths of up to 730 millimeters.
Continue readingInternal Climbing Saw
The internal climbing saw is attached to a platform on a lattice mast inside the structure. The saw cut is made by rotating the platform.
Continue readingExterior Climbing Saw
The exterior climbing saw was developed by LISMAC and MB. This saw is a variant of the Wall Saw combined with a dropping device.